welcome to the web site of the
    arborway committee


Home

Why Restore
Light Rail?

FAQ

Chronology

Community
Support

Documents
and Letters

Speak Out!

News

Photos

Links


Contact

 

 


Arborway Green Line Restoration
Articles

 
As Post-Dig Transit Projects Stall, Lawsuit Looms

By Anthony Flint

From The Boston Globe, 11/8/2004

Unfinished business

In 1990, state officials agreed to improve the region's transit system to reduce air pollution upon the completion of the Big Dig, a $14.6 billion highway project. The state is about to miss a second set of deadlines:

Restoration of the Arborway trolley line in Jamaica Plain, $72 million. Deadline: 2000. State argued unsuccessfully last year that the project was not feasible because of narrow width of Centre Street; no recent action.

Urban Ring, circumferential transit route around Boston, $500 million to $2.3 billion. Deadline for draft environmental impact report: Nov. 30. State says the report will take a few more months.

Blue Line platform- lengthening, $228 million. Deadline: Dec. 31. Work at four Blue Line stations is undone.

Orange Line signal modernization and purchase of 18 additional cars, $367 million. Deadline: Dec. 31. Complete signalization overhaul is incomplete; no cars have been purchased.

Silver Line Phase II, including service to Logan, $601 million. Deadline: Dec. 31.
If the tunnel for buses linking South Station and World Trade Center opens as scheduled, it will not include service to the airport because electric/gas buses will not be available until mid-2005.

Silver Line Phase III, $780 million. Deadline for federal funding: 2005.
Federal Transit Administration has project on "not recommended" list.

Green Line extension to West Medford, $375 million. Deadline: 2011.
State has proposed enhanced bus service instead.

Red-Blue line connector, $193 million. Deadline: 2011. State has suggested dropping the project.
Sources: Conservation Law Foundation, Executive Office of Transportation, Massachusetts Bay Transportation Authority


The state will not make court-ordered deadlines on a half-dozen transit projects promised as a condition for building the Big Dig, inviting a lawsuit that could force the projects to be built on a strict schedule.

Three other Big Dig-linked projects the state is required to build extending the Green Line through Somerville, building a connection between the Red and Blue lines in Boston, and establishing rail service between Boston and T. F. Green Airport in Rhode Island have not been funded or actively pursued, the Conservation Law Foundation says.

"The state found the money to spend $15 billion for the Big Dig. There should have been a parallel effort to find money for the transit piece of the puzzle," said Philip Warburg, president of the foundation. "The state has to be held accountable."

State officials acknowledged that several projects will be late, in some cases for reasons beyond their control, such as a delay in the delivery of subway cars. But they say some need to be revisited to determine whether they are really worth doing.

"We have presented achievable schedules... for the short-term projects and have established an open and public process to examine the long-term projects," said state Transportation Secretary Daniel Grabauskas. "This will be a comprehensive and inclusive process every step of the way."

The commitments were made in 1990 in a deal that cleared the way for the $14.6 billion Big Dig. The rationale was that improving the transit system would give motorists an alternative to the new underground highway system, thus reducing air pollution. The state already missed one round of deadlines on the transit projects in the late 1990s and was ordered by a judge in to meet a new set of target dates.

One deadline to restore trolley service on the Arborway line in Jamaica Plain by the end of 2000 has already come and gone. The state will miss the next deadline, to complete a draft environmental impact report on the Urban Ring circumferential transit line around Boston, by Nov. 30, as well as Dec. 31 deadlines to provide Silver Line bus service to Logan Airport, extend all Blue Line station platforms for six-car trains, and modernize signals and buy 18 new cars for the Orange Line.

The state also appears unlikely to secure federal funding for the proposed underground Silver Line bus tunnel linking Roxbury and South Station, which it is required to have in place by next year.

Attorneys for the Conservation Law Foundation plan to sue Governor Mitt Romney and multiple state agencies, including the Massachusetts Bay Transportation Authority, in federal court on Jan. 3 after the November and December deadlines have formally been missed alleging violations of the Clean Air Act.

If successful, the suit could lead to a judge ordering the state to build all the projects on a strict schedule.

Warburg said the state has dragged its feet on the short-term projects, such as modernizing the Blue and Orange lines, and refused to lay out a plan for funding the longer-range projects, such as extending the Green Line through Somerville to West Medford.

There has been "no transparency" by the T or the Executive Office of Transportation on the status of projects or reasons for delays, he said.

Although the total costs of the transit projects exceeds $5.4 billion, Warburg said that outlay would still be a fraction of the cost of the Big Dig.

Equally important, said Carrie Schneider, an attorney for the foundation, was that the state entered into a legally binding agreement to undertake the projects.

"The Big Dig would not have gone forward without these requirements," she said. "This wasn't just a nice idea afterwards."

Douglas Foy, Romney's secretary for Commonwealth Development, declined to answer questions about the state's progress on the transit projects. Foy is former president of the Conservation Law Foundation, and helped put together the 1990 pact forcing the state to commit to the projects.

Jon Carlisle, spokesman for the Executive Office of Transportation, said there was a hitch in the delivery of Blue Line cars that pushed that modernization project back by at least a year. In addition, he said, the T was going to retrofit old Blue Line cars to satisfy the requirement for 18 new Orange Line cars, but after spending $1 million concluded that it would be too costly.

As for Silver Line service to the airport, Carlisle said that hinges on the delivery by mid-2005 of so-called "dual mode" buses, which would convert from electric power to compressed natural gas in their trips to Logan.

The state continues to lobby for federal funds for the Silver Line downtown tunnel linking Roxbury and South Station, Carlisle said, and the draft environmental impact report on the Urban Ring will be a few months late as final revisions are done.

The Arborway trolley restoration, the Green Line extension, and the Red-Blue connector should be reexamined, Grabauskas said in a Sept. 2 letter to Robert Golledge, the commissioner of the Department of Environmental Protection, which is responsible for enforcing the transit commitments. The state would like to explore whether other transit projects provide equal or better clean air benefits, Grabauskas wrote.

Anthony Flint can be reached at flint@globe.com

© Copyright 2004 The New York Times Company

From www.boston.com/globe.