|
Arborway Green Line Restoration
Documents
Testimony of Franklyn P. Salimbene, Esq., Chair, Arborway
Committee before Executive Office of Environmental
Affairs (EOEA) regarding Expanded Environmental Notification Form,
Arborway Green Line Restoration Project
12 May 2003
TABLE
OF CONTENTS
INTRODUCTION
I. WHY THE DEP DECISION TO RESTORE ARBORWAY GREEN LINE
SERVICE WAS RIGHT
II. ARBORWAY EENF: Context
A. A single EIR
B. The Arborway regulation 310 CMR 7.36 (2)(d)
C. Arborway Rail
Restoration Project Advisory Committee (ARRPAC)
D. Environmental Justice
III. ARBORWAY EENF: Comments
A. Transportation
improvements (EENF, pp. 1-2, 1-3)
B. Costs (EENF, pp. 1-3,
1-12, 1-13)
C. No additional
alternatives analysis (EENF, pp. 2-1 to 2-4)
D. Air quality impacts
(EENF, pp. 4-8, 4-9)
E. Simulation software
packages and projections (EENF, p. 4-1)
F. Proposed mitigation
measures (EENF, p. 5-2)
G. Additional comments:
parking (EENF, p. 3-9) and cycling (EENF, p. 3-5)
H. Factual inaccuracies
IV. CONCLUSION
REFERENCED DOCUMENTS AVAILABLE ONLINE
(First reference to each is
linked in text)
INTRODUCTION
The Arborway
Committee (AC) agreed with the order of the
Department of Environmental Protection (DEP) dated November 7,
2001, to restore Arborway Green Line service.
For reasons set out below, AC believes that the order made both good
transportation and good environmental sense. Further, AC believes that
restoring Green
Line service to the entire Arborway Corridor is consistent with the
Governor’s “smart growth” policies that put quality public transit
where people live and provide the fastest service to their destination.
AC submits the following testimony regarding the Arborway project
Expanded Environmental Notification Form (EENF). While agreeing and
disagreeing in parts with the EENF, AC notes for the record that the
EENF is at times both overly political and factually inaccurate.
Included in this AC testimony and incorporated by reference is a copy
of AC’s July 10, 2001 testimony before
DEP regarding the request by the Executive Office of Transportation and
Construction to substitute the Arborway project. The 2001 testimony
provides
background to this testimony and is referenced throughout. The
testimony
along with appendices is found in the accompanying blue booklet.
I. WHY THE
DEP DECISION TO RESTORE ARBORWAY GREEN LINE SERVICE WAS RIGHT
In the late 1890s the City of Boston made a fundamental decision to
remove transit vehicles from downtown roadways. The construction of the
Tremont Street subway and its expansion to the Back Bay were key to
providing
a public transit system that neither added to downtown congestion nor
suffered delays because of it. According to Vukan R. Vuchic, Professor
of Transportation Engineering at the University of Pennsylvania, this
decision “gave Boston a national reputation as a leading city in
far-sighted transportation planning.” (Vuchic Arborway Testimony, p. 1,
2001)(A complete copy of Vuchic’s testimony can be found in the
accompanying blue booklet at Appendix 8.)
Beginning in the 1950s, however, the MBTA and its predecessor, the
Metropolitan Transit Authority, began the systematic dismantling of the
very infrastructure that contributed to Boston’s national reputation.
Streetcar lines that served city neighborhoods connecting them directly
into the central subway were abandoned in favor of bus service. Where
this substitute bus service did
not go directly downtown, but dropped riders at subway stations that
required a transfer to complete the journey, ridership suffered. The
most prominent example is the Route 57 bus service from Brighton and
Allston to Kenmore
Square that replaced the Green Line’s A-Branch to Park Street. Where
bus
service did go directly downtown, as with the Route 43 bus service that
replaced
the Tremont Street Green Line, the bus service both added to downtown
congestion and suffered delays because of it.
In 1985, continuing its systematic dismantling of transit
infrastructure, the MBTA moved to convert the Arborway Green Line
service to a bus service, the Route 39. Not only did the Route 39 bus
service introduce into the Back Bay 800 daily bus trips, but it also
required passengers to transfer into the subway in order to reach the
final destination, Park Street.
In his testimony regarding the MBTA’s Arborway alternatives analysis,
Vuchic noted that operating buses in the city center represents a major
deterioration in transit service. (Vuchic, p. 2, 2001) The facts
confirm
his testimony. Ridership on the Route 39 has fallen from 28,000 in 1988
to 17,400 today. (MBTA Ridership and Service Statistics, pp. 2-10,
2-11,
1988;
Arborway Alternatives Analysis , p. 9, 2001)
Vuchic also noted that conversion from rail to bus invariably results
in a significant lowering of vehicle performance. (p. 2) Again, facts
confirm his testimony. In August 1996, the MBTA issued a report on
Route 39 bus operations that acknowledged the operational difficulties
associated with running a bus in traffic for the full 10.3-mile route
into and out of the Back Bay. The report stated that “customer
complaints routinely show that schedule reliability is the primary
concern of Route 39 passengers.” It went on: “This is reasonable since
poor adherence to schedules contributes to uneven
vehicle loading, bunching, delayed buses, and missed connections.”
(Service
Review: Route 39, pp. 2-3, 1996) Route 39 bus operations today are a
confirmation
of both the validity of Boston’s 1890 transit strategy of putting
transit
underground and the folly of the more recent MBTA policy of dismantling
urban
rail transit infrastructure that connects into the central subway
system.
Viewed in this context, therefore, the November 7, 2001 decision by
DEP to restore Arborway rail service was a decision of historic
proportions.
- First, it
was a reaffirmation of Boston’s nationally recognized policy of the
1890s that removed public transit from the downtown traffic mix so that
transit neither added to congestion nor suffered delays because of it.
- Second, it
was a reversal of the MBTA’s 50-year policy of systematically
dismantling rail infrastructure in heavily transit-dependent city
neighborhoods and converting to bus service that significantly eroded
transit reliability and
air quality in the very locations where these factors mattered most.
- Third, it
was a recognition that while Arborway Green Line service resumption
created some challenges along portions of its route in Jamaica Plain,
those challenges were in the long run far more manageable and less
costly to remedy than the challenges associated with accommodating ever
growing numbers of buses and bus routes in an increasingly more
congested downtown traffic mix.
- Fourth, it
was a pledge to increase public transit ridership and reduce toxic
emissions by providing zero-emission Arborway Green Line service that
is faster than bus to downtown Boston; creates direct connectivity to
the Red, Blue, and Orange Lines; and provides significantly higher
transit capacity along the heavily transit-dependent Arborway Corridor.
II.
ARBORWAY EENF: Context
A. A single EIR
AC endorses the MBTA’s request to file a single EIR. The endorsement is
based upon the long, public, comprehensive, and inclusive process
relating to the Arborway transit project. Most significantly, the
Arborway project has been the subject of three alternative analyses and
three accompanying public processes. The 1987 Arborway Study was a
16-month process during
which more than a dozen public meetings were held in the neighborhood.
A
public hearing on the study’s conclusions was held in January 1988. In
1999,
a second alternatives analysis, The Arborway Study: Final Report was
issued. This study and the proposed DEP ruling were the subject of two
public hearings and lengthy public comment periods in March and May,
1999. From January
2000 to April 2001, a third alternatives analysis was undertaken,
Arborway
Alternatives Analysis: Final Report. During this 16-month period,
approximately
a dozen public meetings were held in the neighborhood. These meetings
were
ordered by DEP as a result of the 1999 public process in order to
solicit
the widest possible public input. They were well publicized, well
attended,
and well covered by the local press. The issuance of the report was
followed
by a public hearing in July 2001 and a lengthy public comment period.
In addition to these studies and hearings, additional public process
occurred in relation to the following events. In 1986, an Arborway
Green Line restoration referendum question appeared on the State ballot
in Jamaica Plain. In 1989, a memorandum of understanding between the
City of Boston and the MBTA to restore Green Line service was
negotiated by the Jamaica Plain legislative delegation. In 1991, DEP
conducted public hearings as part
of the process that created 310 CMR 7.36 (2)(d) mandating the
restoration of Arborway Green Line service. Also in 1991, the
legislative delegation proposed and won inclusion of the Arborway
project in the State transportation bond bill. From 1991 through 1996,
the MBTA Arborway Advisory Committee conducted dozens of public
meetings attended by representatives of residents, businesses, and the
City of Boston to discuss implementation and operation of restored
Arborway Green Line service. In 1995, the legislative delegation again
proposed and won inclusion of the Arborway project in that year’s
transportation bond bill. From 2002 through 2003, the MBTA has
conducted more than a dozen meetings in the neighborhood as part of the
Arborway Rail Restoration Project Advisory Committee (ARRPAC) process.
Finally, in 1987, 1996, and 2001, the Jamaica Plain Neighborhood
Council conducted public hearings preceding its voting to support the
Arborway restoration project.
The EENF process is, therefore, only one
step in the very long history of meetings, studies, and other
initiatives relating to the Arborway Green Line restoration project.
This long, public, comprehensive, and inclusive process regarding
Arborway transit service warrants the submission of a single EIR.
B. The
Arborway regulation 310 CMR 7.36 (2)(d)
Very much a part of this process has been DEP
regulation 310 CMR 7.36 (2)(d) , which mandates Arborway Green Line
restoration. This public transit regulation along with several others
was promulgated in 1991. Together, these regulations were a
counter-balance to what was rightly viewed at that time as a projected
excessive expenditure by the State in favor of the private automobile
represented by the Central Artery project.
Ironically, some opponents have come forward recently to lobby the
State to abandon its regulatory commitment to the Arborway project
because Green Line service, in their view, would have a negative impact
on automobile access and parking along a short section of the Green
Line route in Jamaica Plain. Putting aside the legal action that a
reversal of the Arborway transit commitment would invite, the
abandonment of any transit commitment so as to facilitate automobile
access and parking would contradict the very purpose and nature of the
transit regulation, which is to reduce reliance upon the private
automobile. To take any action, therefore, that facilitates
automobile access and parking at the expense of Green Line restoration
in the Arborway Corridor simply invites more automobile traffic and the
negative air quality impacts that the regulation is intended to remedy.
It would
stand the transit regulation on its head.
C. Arborway
Rail Restoration Project Advisory Committee (ARRPAC)
None of this is to deny that restoration of Arborway Green Line service
is without challenge. It is important to remember, however, that the
entire Central Artery road-building project has been a challenge of
monumental proportions. The challenge of restoring a two-mile streetcar
line, which is a Central Artery commitment, pales in significance to
the road project.
Nonetheless, to provide both a forum for raising issues and a mechanism
for resolving them during the Arborway project, the MBTA has
constituted the Arborway Rail Restoration Project Advisory Committee
(ARRPAC). Chaired by William Lieberman, a nationally recognized expert
in urban light rail
design and operations, and Barbara Boylan, AIA, the project manager,
ARRPAC
is playing a positive role in the restoration process.
ARRPAC represents a wide range of interests. It represents Jamaica
Plain businesses and residents. In fact, when formed, 25% of its
membership was composed of Jamaica Plain business leaders. It also
represents people who do not live in Jamaica Plain, but who live, work,
and shop within the Arborway Corridor from downtown, the Back Bay, and
the Fenway, to the Longwood Medical Area, Roxbury, and Mission Hill. In
addition, it represents elected public officials and a number of City
of Boston agencies.
Working from this representative base ARRPAC has been thoughtful and
open in its deliberations. For instance, the first major issue
discussed by ARRPAC related to transit stop locations for the restored
Green Line service. (EENF, pp. 1-10 to 1-12) Several concerns were
raised by business interests, many of whom feared that automobile
parking would be lost in the Centre Street business district. To this
end, ARRPAC agreed with the proposal of the Vice President of the
Jamaica Plain Business and Professional Association (BAPA) that
outbound stops be located at either end of the business
district rather than in the middle. The objective was to smooth traffic
flow within the business district and to create some new on-street
parking
where the current Burroughs Street bus stop would be discontinued.
Retaining the outbound stop at the southern end of the business
district near Eliot Street as suggested by the BAPA Vice President
posed a dilemma, however. While the owner of Little Peach at the corner
of Eliot Street wanted the stop to remain directly in front of his
shop, his neighbor, AAA Appliance, did not want the stop there. AAA
claimed that the stop would interfere
with appliance deliveries to his store. ARRPAC reviewed the situation
and
decided to retain the stop as located because AAA had ample room to
take
deliveries through a rear entrance. (Appendix 1 herein, photo)
As a further
example of ARRPAC’s thoughtfulness and inclusivity, agreement was
reached
that Green Line stops not be created directly opposite each other, but
that stops be staggered along the route so as to provide ample room for
emergency vehicle maneuverability. As ARRPAC works through these and
similar
issues, members know from prior history that Green Line service is
compatible
with retail activities and emergency access. ARRPAC has a good
practical
base from which to work.
ARRPAC is an important part of the
restoration process. Not all issues raised can be resolved to
everyone’s satisfaction. Doubtless, there will be other issues that
will arise to demonstrate the point. Nevertheless, ARRPAC remains a
positive, open, and representative mechanism for resolving differences
of opinion.
D.
Environmental Justice
One other important element that comprises the context of the Arborway
EENF is Environmental Justice (EJ). Arborway restoration is an
Environmental Justice project. Forty percent of Jamaica Plain residents
are either Afro-American or Hispanic. (EENF, p. 3-28) In addition,
13.7% of residents within the study corridor are persons living in
poverty. (EENF, p. 3-31) The MBTA also has reported that 20% of Route
39 riders have annual household incomes below $20,000, and 40% of
riders do not own an automobile (Arborway Alternative Analysis, p. 9,
2001)
The replacement of a high pollution, internal combustion bus service
with a zero-emission, electric transit line in a heavily
transit-dependent, poor urban neighborhood is the hallmark of
Environmental Justice. While not disregarding the overall regional air
quality benefits that come from removing people generally from their
automobiles and putting them on public transit, Professor Vuchic
comments that “buses produce pollution not dispersed through the
region, but directly in the streets. Their emissions are actually most
intensive when they accelerate from stops, in areas of the greatest
concentration
of pedestrians.” (Vuchic, p. 3) In Jamaica Plain this is a critically
important
fact. The Boston Globe has reported that overall, Jamaica Plain has a
higher
level of reported asthma cases than the city-wide Boston average.
Further,
portions of Jamaica Plain have the highest levels of reported asthma in
all
of Massachusetts.
Coupled with the Governor’s recent apparent decision to reallocate
transit dollars from commuter rail projects to rail projects within the
urban core, DEP’s November 2001 order to restore Arborway Green Line
service clearly promotes the Environmental Justice agenda. Arborway
Green Line restoration will reduce high concentrations of toxic
emissions in the very places where people of color and poverty live.
Before moving from this topic, the Arborway Committee (AC) notes that
the EENF, while concluding that “the Jamaica Plain area meets the
criteria of an EJ population” with more than 40% Afro-American and
Hispanic residents, surprisingly concludes that only 4.4% of the
population within the Arborway EENF study area is Afro-American or
Hispanic. (EENF, p. 3-30) This seeming discrepancy between the overall
Jamaica Plain minority population and the minority population within
the EENF study area may result from the methodology used in reaching
the conclusion or from seeming statistical omissions.
- First, the
study area used for the EENF does not correlate with the 2001 study
area used by the MBTA for calculating Arborway ridership. To calculate
the minority population in the study area the EENF used U.S. census
blocks while to
calculate ridership the MBTA used straight lines running parallel along
both sides of the Green Line alignment at three-quarters of a mile
distance.
This is known as the ridership “catchment” area. Measuring the
population
characteristics within the catchment area may be a more reliable
measure
of the ethnic characteristics within the Arborway Corridor.
- Second,
Table 3.6-2 (EENF, p. 3-30) omits from the list of census blocks
several blocks within sight of the Green Line alignment that have heavy
concentrations of minority residents. For example, Census Tract 812
Block Group 2, Census Tract 1206 Block Group 1, and Census Tract 1206
Block Group 2 as found
in Figure 3.6-1B (in the map appendix to the EENF) are all excluded
from
the Table and the calculation.
- Third, the
methodology used to demonstrate the ethnic characteristics of the study
area takes no account of actual ridership characteristics. Even a
casual observer of Route 39 ridership would note that during certain
periods of the day, a majority of passengers are members of racial and
lingual minorities. These, however, are not incorporated into the
ethnic calculation.
Utilizing these
alternative measures would likely result in an assessment of ethnic
characteristics of the population to be served by the Arborway Green
Line that more closely comports to the overall ethnic composition of
the Jamaica Plain neighborhood.
III.
ARBORWAY EENF: Comments
A. Transportation improvements (EENF, pp. 1-2, 1-3)
AC concurs that the EENF captures the importance of Arborway Green Line
restoration as a project that both improves transportation services and
distributes these improved services more equitably within the urban
core.
To wit, Arborway restoration will:
- promote “an
economically strong urban core that is not dependent upon automobile
access;”
- “comply
with state air quality strategy plans;”
- promote an
“equitable distribution of transportation services across the
metropolitan area;” and
- “support
regional mobility and environmental goals through cost-effective
transportation measures.” (EENF, pp. 1-2, 1-3)
AC would add that the Arborway project will promote an economically
strong urban core that is not only not dependent upon automobile
access,
but also not dependent upon bus access. As Vuchic has stated, buses are
“a major contributor to street traffic congestion.” (Vuchic, p. 2,
2001)
In the context of current Route 39 bus service, the congestion impacts
are
magnified. Route 39 operates 401 inbound and 401 outbound trips in the
Back
Bay every weekday. Removal of these buses from the urban core will play
a significant role in decreasing Back Bay congestion. In 2001, in
seeming
agreement with Vuchic, the Boston Transportation Department (BTD)
responded
to the MBTA’s proposal to extend Route 39 service to Park Street as
follows:
“The City cannot determine if this transportation link is effective
unless
further detailed analysis is undertaken.” BTD
Commissioner d’Amato went on to call into question the capacity of
Tremont Street to accommodate additional 60’ articulated buses as well
the overall impact of the extended service on the streets
leading to and rounding Boston Common. (AC Testimony, Appendix 14,
2001,
in the accompanying blue booklet)
B. Costs
(EENF,
pp. 1-3, 1-12, 1-13)
AC concurs that the Arborway project as “a cost-effective
transportation measure.” (EENF, p. 1-3) AC has continually maintained
that the costs of Arborway Green Line restoration as presented by the
MBTA in the past were overly inflated and that the costs of the
alternative CNG bus proposal were significantly underestimated. (AC
Testimony, pp. 5-8, 2001, in the accompanying blue booklet) In its 1999
and 2001 submissions to DEP, for example, the MBTA was adamant that
restoring Green Line service would require the purchase of additional
Green Line cars at a cost of $45.9 million. Contesting this point, AC’s
2001 testimony demonstrated the adequacy of the current fleet to
accommodate restored Arborway service. (AC Testimony, pp. 5, 7, and
Appendix 4, in the accompanying blue booklet) It is refreshing to see,
therefore, that
the MBTA now admits to the possibility that new Green Line cars might
not
be necessary after all. (EENF, p. 1-13). This is indeed progress.
None of this should lead EOEA to conclude that AC agrees with the
remainder of the MBTA’s cost calculation for the project, which is
alleged to be $58 million. (EENF, p. 1-12) In 2001, the MBTA estimated
the cost of Green Line restoration to be $30.8 million absent the cost
of additional cars, project design, mitigation, and project
administration. Now the EENF calculates the cost to have risen to $45.5
million absent the same factors. It is not clear why within the
intervening two years, with inflation and interest rates
at very low levels, the cost of the project has increased by $15 million. Nonetheless, whether $30.8 million or $45.5
million or $58
million, the project is cost effective. By way of comparison, the MBTA
has agreed to upgrade station stops on the Indigo Line from Hyde Park
to
South Station at a cost of approximately $70 million. The $70 million
covers
the upgrade of only eight stations.
C. No
additional alternatives analysis (EENF, pp. 2-1 to 2-4)
AC concurs with the MBTA that “no additional alternatives analysis is
necessary in the EIR….” (EENF, p. 2-4) The reasons are legal,
practical, and fiscal.
Legally, further alternatives analysis is not justified under the
regulation. Regulation 310 CMR 7.36 (4)(a) states:
EOTC may substitute other transit improvement projects in place of
those listed in 310 CMR 7.36. To replace a project EOTC must
demonstrate to the Department that a specific project listed in 310 CMR
7.36 is infeasible….
The regulation invites a substitute project, and by implication the
alternatives analysis necessary to support such a project, either
pending
an infeasibility determination of the listed project or subsequent to
an
infeasibility determination of the project. Once the listed project is
ruled feasible, however, as is the case with Arborway Green Line
restoration,
the reason and purpose for an alternatives analysis cease to exist. If
the project is deemed feasible, there is no legal basis for
substitution.
If there is no legal basis for substitution, there is no legal reason
for
performing an alternatives analysis. An alternatives analysis would
serve
no purpose.
Practically, a further alternatives analysis would be ill-considered.
First, any alternative project would be governed by 310 CMR 7.36
(2)(d), which mandates “restoration” of Arborway service. Arborway
service has
been defined as service from Arborway to Park Street. (DEP Decision on
Arborway Restoration Petition, p. 2, September 1, 2000) The alternative
project would, therefore, have to provide either a direct one-seat bus
ride to Park Street, or a transfer to Park Street from some
intermediate
point, e.g., Ruggles Station or Copley Square. The direct one-seat ride
by bus to Park Street would create more problems than it would solve
(Vuchic)
and an intermediate transfer would incur a significant ridership loss
and
concomitantly far higher emissions than Green Line restoration. Second,
an alternatives analysis would be ill-considered because it would be
conducted
by the MBTA, an entity which has come to merit the distrust with which
many
view it. Third, further alternatives analysis would needlessly incur
additional
delay in restoring Green Line service, which was mandated to have been
restored
in 1997. Fourth, further alternatives analysis would require EOEA and
DEP
to engage in additional and repetitive oversight of a project that has
already
consumed an inordinate amount of the agencies’ time and resources.
Fiscally, more alternatives analysis
would add to the cost of the Arborway project. The expenditure of funds
for the implementation, conduct, and oversight of repetitive and
duplicative studies is not justifiable in good or bad
economic times.
D. Air
quality impacts (EENF, pp. 4-8, 4-9)
AC does not agree that the “air quality study presented in the EIR will
identify and quantify the air quality benefits of the Arborway
Restoration Project.” (EENF, p. 4-8) Because the study area does not
include the entire Arborway Corridor, only a partial evaluation of air
quality benefits will be undertaken. No account will be taken of air
quality benefits of restored service in the northern portion of the
corridor from Heath Street to the Back Bay.
For example, the EENF proposes quantifying benefits resulting from the
elimination of diesel bus service from Heath Street to Forest Hills.
(p. 4-8) Although Arborway restoration will also remove diesel bus
service from Heath Street to the Back Bay, the EENF does not propose a
similar evaluation of air quality benefits for this portion of the
route.
Further, the EENF proposes quantifying “any increases in the emission
of pollutants of concern…caused by increased traffic congestion or
delays following the restoration of light rail service….” (p. 4-8)
While the notion that increased congestion would result from Arborway
restoration is ill-founded and disputed by two previous studies (1987
and 2001), the EENF does not propose quantifying any decreases in
emissions resulting from the removal of 800 buses per day from the
traffic mix along the northern portion of the
Arborway Corridor. For instance, what is the air quality impact of
removing 800 buses per day from Copley Square, or from Brigham Circle,
or from the intersection at Huntington Avenue and Ruggles Street?
As contemplated, the EENF will provide
only a partial evaluation of
the air quality impacts of restored Arborway service. Therefore, AC
recommends extending aspects of the air quality analysis to the
northern portion of the corridor.
E.
Simulation software packages and projections (EENF, p. 4-1)
AC supports the utilization of either the VISSIM or PARAMICS simulation
software packages for calibrating the operations parameters of restored
Green Line service. It appears that these packages are better suited
for
light rail operations than is the standard package used by the Boston
Transportation Department. The BTD package is not sophisticated enough
to account for urban light rail operations.
AC understands, however, that the value of any software package depends
upon the information fed into it. For example, the mesoscale analysis
to be conducted by the Central Transportation Planning Staff (CTPS)
(EENF,
p. 4-9) raises some concern for AC in that the analysis will be based
upon
ridership analyses already developed by CTPS. Previous CTPS ridership
and
emissions projections made for the Arborway alternatives analysis that
was submitted to DEP in July 2001, raised many questions regarding
their
reliability. Yet, these projections, which AC rejected as consistently
underestimating
both potential ridership and beneficial air quality impacts of restored
Arborway Green Line service, appear in the current EENF. (pp. 1-8 and
4-
8) As AC stated in its 2001 testimony, “…EOTC and its consultants have
submitted
a report so biased in favor of its proposed bus substitute as to be
meaningless.” (AC Testimony, pp. 9-12, 2001, in the accompanying blue
booklet)
For these reasons, AC cautions EOEA
against relying upon any statements in the current EENF that project
ridership or emissions levels resulting from Arborway restoration. (pp.
1-8 and 4-8) Further, AC requests that ARRPAC have ready and regular
access to CTPS during the running of any and all computer analyses for
the EIR.
F. Proposed
mitigation measures (EENF, p. 5-2)
AC makes the following recommendations regarding mitigation measures
proposed for study in the EIR:
- A one-way
traffic flow system for Centre and South Street is both impractical and
unnecessary. This measure should be omitted from study.
- Elimination
of parking at certain locations along Centre and South streets might
prove beneficial. This measure should be studied in consultation with
ARRPAC.
- Creating a
pedestrian mall along certain sections of the corridor is a novel
suggestion. While this measure may meet with initial resistance and may
ultimately prove to be impracticable, it ought to be studied.
- From the
language of the proposed emergency response controls mitigation
measure, it is unclear what is contemplated by the MBTA. To assist in
fashioning an emergency response protocol, AC suggests that the MBTA
undertake a review of emergency protocols that exist in other North
American cities that operate light rail systems in street, e.g.,
Toronto and Philadelphia. The MBTA should also consult with experienced
members of the Boston Carmen’s Union. That having
been said, however, it remains AC’s view that concern regarding
emergency response is exaggerated and seems incorporated into the EENF
for political purposes only. (AC Testimony, pp. 21-22, and Appendices
21 and 22, in the accompanying blue booklet)
- Transit
control measures are important elements of mitigation. Headways, dwell
times, and consist size are, therefore, important to consider.
Regarding
headways, 5-minute, 6-minute, and 7-minute peak headways should be
studied.
Regarding consist size, AC encourages the MBTA to include in its study
the operation of single car service. It is clear from Arborway Green
Line
service in the 1980s that double-car operation during peak is likely
necessary.
The great promise of Arborway Green Line service is its potential to
increase
transit ridership significantly over current Route 39 passenger counts.
For instance, when Arborway Green Line service last operated in 1985,
it
carried 50,000 daily riders, or 15.3 million riders annually. (Arborway
Study, p. 5, 1987) While essential during rush hour, however,
double-car
operation seems neither required nor desirable during off-peak weekday
hours
and during weekends. Therefore, all impacts and mitigation measures
studied
for double-car service should also be studied for single car service.
- Traffic
signal coordination options should be studied.
- Redesign of
on-street parking to optimize parking capacity should be studied.
- The
construction of new parking lots or garages adjacent to Centre Street
in the vicinity of new station locations should not be contemplated or
studied for the EIR. In the context of the southern portion of the
Arborway Corridor, new parking lots and garages would constitute poor
urban planning. Such lots and garages would act as magnates for
commuters to drive to Jamaica Plain to catch the Green Line. This would
exacerbate traffic issues rather than alleviate them. What might be
helpful, however, is an investigation of the benefits of
converting to public use the existing privately owned and
under-utilized parking lot behind the Galway House in the Centre Street
business district. This could be studied for use as a long-term parking
facility for business owners and employees in the business district or
as a second short-term lot to supplement the public lot on the west
side of Centre Street.
- Finally, although not mentioned amongst the
mitigation measures, BTD
must be encouraged to become fully engaged in the Arborway project. BTD
must play a positive and proactive role in preparing a traffic
management
plan for both the immediate and future time periods.
G.
Additional comments: parking (EENF, p. 3-9) and cycling (EENF, p. 3-5)
AC has consistently maintained that issues of parking are not within
the contemplation of 310 CMR 7.36 (2)(d) and seem to be raised for
political purposes only. AC also maintains that parking impacts are not
relevant to the EENF process. Nevertheless, AC notes with interest the
MBTA’s assessment that parking along the study corridor is not at
capacity. “Occupancy rates in excess of 85 percent generally indicate
that parking is at capacity.” (EENF, p. 3-9) Table 3.1-3 indicates a
range of occupancy between 60.89% and
76.47%. While there is consensus that parking along the Arborway
Corridor, and particularly within the business district, ought to be
optimized, current occupancy rates appear to allow for some flexibility
in reaching decisions regarding parking.
Regarding cycling, AC believes that every reasonable measure consistent
with restoration of Green Line service ought to be taken to assure
cycling safety along the Arborway Green Line alignment. Such safety
measures undertaken ought to be proportionate to cycling demand,
however. It is instructive to note that the number of cyclists along
the corridor is generally “less that 10 per hour” although during rush
hour the number sometimes reaches 20. (EENF, p. 3-5) This number pales
in comparison to the thousands of public transit riders in the
corridor.
The EENF concludes that cyclists generally seem not to choose to ride
along Centre and South streets because the narrowness of the streets
does not provide an adequate or safe cycling environment. While cycling
should be encouraged as an alternative means of transit, it should not
be encouraged under any transit scenario along routes that are already
too narrow for safe cycling. Fortunately, however,
there are two safe and convenient alternatives
for cyclists in Jamaica Plain. These are the Jamaicaway bike path and
the
Southwest Corridor bike path, both within a half mile on either side of
Centre and South streets. (AC Testimony, p. 20 and Appendix 20, 2001,
in
the accompanying blue booklet)
H. Factual
inaccuracies
For the record, AC notes the following inaccuracies and misstatements
in the EENF:
- “Approximately
90 diesel bus one-way trips per day will be removed from service.”
(EENF, p. 4-8) This is inaccurate. The number of diesel bus one-way
trips per day that will be removed from service as a result of Green
Line restoration is 401. (Service Review: Route 39, p. 4, 1996) A
casual review of the current Route 39 timetable will confirm the number.
- “Although
no vibration induced damage from train operations is predicted, ground
borne vibration generated by Green Line trains will result in an
increase of
vibration events per day, rather than higher levels.” (EENF, p. 5-3)
This
is inaccurate. The number of vibration events per day resulting from
Green
Line restoration will decrease from the current 802 events caused by
passing
buses to less than 600 caused by passing streetcars. For example, the
current
Route 39 bus schedule lists rush hour bus service at every 4 minutes.
Green
Line rush hour service has never been contemplated as operating at
4-minute
headways. In fact, the Arborway Alternatives Analysis contemplated
6-minute
headways. (Arborway Alternatives Analysis, pp. 12, 18, 2001) Therefore,
Green
Line service is bound to result in a reduction of vibration events, not
an
increase.
- “The Orange
Line also serves the corridor and runs in the Southwest Corridor from
downtown Boston to the Forest Hills Station…approximately 0.5 miles
east of the Arborway corridor.” (EENF, p. 1-7) This is misleading.
While portions of the Arborway Corridor and the Southwest Corridor are
within one-half mile of each other, other portions of the corridors are
more than one-half mile away from each other. (This is similar, for
example, to the Riverside and Beacon Street Corridors in Brookline.)
Further, and more importantly, because Orange Line station locations
are spread out along the corridor, the walking distance to an Orange
Line station for most residents within the Arborway Corridor,
particularly along its western and northern perimeters, is far more
than
one-half mile. In addition, the Arborway Corridor serves destinations
different
from those in the Southwest Corridor. For example, the following
destinations
among others are in the Arborway Corridor, but not in the Southwest
Corridor:
Jamaica Pond and much of the Pondside neighborhood, Olmstead Park, the
VA
Hospital, the Brigham and Women’s Hospital, Children’s Hospital,
Arlington Street, Commonwealth Avenue, and most of South Huntington
Avenue.
-
“The Arborway Streetcar Restoration Project may require issuance of a
Curb Cut Permit from the Metropolitan District Commission (MDC)….”
(EENF, p. 1-13) This is unlikely. Access for streetcars into the
Arborway Yard already
exists through current curb cuts on both the western and eastern sides
of
the Washington Street-Arborway intersection. With proper planning, no
additional
cuts would be needed.
IV.
CONCLUSION
While AC is determined to work with the MBTA, BTD, EOEA, and DEP to
bring Arborway Green Line restoration to a successful conclusion, two
items
of concern still need to be addressed.
First, DEP has not yet approved a final schedule for the design and
construction of the Arborway project. In its order of November 7, 2001,
DEP stated: “The Department requires by this letter that a schedule for
the design and construction of the Arborway Project be provided to the
Department by December 31, 2001. The schedule shall include benchmarks,
milestones and action items and shall be subject to approval by the
Department.”
To date, it appears that the MBTA has not complied with this order. AC,
therefore, urges EOEA and DEP to enforce the order either by prevailing
upon the MBTA to comply or by imposing theirown schedule on the MBTA.
Second, the MBTA has provided no funding for the construction of the
Arborway project in its current Capital Improvement Program 2003-2008
(CIP). AC views this as a breach of the MBTA’s obligation under the
order of November 7, 2001. It is also a violation of the State’s
obligations under the State Implementation Plan.
|